Quisque quam lacus, hendrerit in enim sed, cursus vulputate urna. Nullam et lacinia ante. Cras ac urna nec urna gravida cursus. Integer suscipit id diam a semper. Proin pulvinar erat purus, ac porttitor turpis tincidunt non. Integer mattis, ante id fermentum venenatis, tortor libero ullamcorper nunc, eget sollicitudin risus eros a velit. Nulla in diam pharetra, volutpat nisi vitae, dictum dui.
Construction is expected to last for three and a half years, followed by up to six months of commissioning. We have divided the construction project into three distinct packages. There will be some overlap between these and you can find more information below. We have also included a summary of the pre-construction tasks completed to date. Precise timings for all activities are subject to change as the construction programme evolves and we will add live status updates as the project progresses.
Pre-construction and enabling activities
Pre-construction details placeholder
Vegetation Clearance
Deliver materials to the temporary compound, prepare holes for fence posts, and install all fence posts along with gate pads.
Read More
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Quisque fermentum justo erat, sit amet congue ex malesuada a. Aliquam erat volutpat. Fusce egestas cursus nulla id scelerisque. Sed ut quam blandit, congue odio vel, luctus tortor. Integer porttitor justo nisi, sed venenatis nisl faucibus vel. Etiam fermentum quis elit nec viverra. Fusce eu eros nec velit vestibulum condimentum id vel tellus. Integer at convallis mi, sed blandit nibh.
Cras ac massa sodales, pretium ante at, rutrum risus. Nunc efficitur est metus. Phasellus rutrum odio quis ex tempus, sed hendrerit nisl maximus. Orci varius natoque penatibus et magnis dis parturient montes, nascetur ridiculus mus. Nam nec risus sed est bibendum sagittis. Vivamus massa mi, malesuada rhoncus ipsum id, fringilla mattis turpis. Nullam mattis id justo vitae rhoncus. Donec semper viverra ante ac commodo. Mauris et ex at erat egestas sollicitudin quis id libero. Quisque mi mi, facilisis nec tempor ac, feugiat at mi. Duis sollicitudin quis augue sit amet consectetur. Aenean ipsum diam, bibendum a turpis in, tempus ultricies lacus. Etiam varius risus eget diam faucibus eleifend. Donec laoreet justo et pretium porttitor.
Etiam in purus eget mauris consectetur fringilla. Nam ac odio sed erat ullamcorper luctus. Aliquam erat volutpat. Sed consequat dignissim metus elementum aliquam. Donec vitae justo vestibulum, fringilla eros vel, venenatis lectus. Vestibulum orci felis, sodales molestie porta eget, efficitur id sapien. Praesent ultrices, felis eget suscipit sollicitudin, ipsum diam mollis metus, et fermentum mi risus sed enim. Praesent commodo, sapien nec ullamcorper hendrerit, tortor erat consectetur sem, ultricies tincidunt diam risus nec metus.
Welfare Cabins at New Bridge Lane
Construction of acoustic fence – this provides a noise barrier between 10 Newbridge lane and the new site entrance.
Read More
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Quisque fermentum justo erat, sit amet congue ex malesuada a. Aliquam erat volutpat. Fusce egestas cursus nulla id scelerisque. Sed ut quam blandit, congue odio vel, luctus tortor. Integer porttitor justo nisi, sed venenatis nisl faucibus vel. Etiam fermentum quis elit nec viverra. Fusce eu eros nec velit vestibulum condimentum id vel tellus. Integer at convallis mi, sed blandit nibh.
Cras ac massa sodales, pretium ante at, rutrum risus. Nunc efficitur est metus. Phasellus rutrum odio quis ex tempus, sed hendrerit nisl maximus. Orci varius natoque penatibus et magnis dis parturient montes, nascetur ridiculus mus. Nam nec risus sed est bibendum sagittis. Vivamus massa mi, malesuada rhoncus ipsum id, fringilla mattis turpis. Nullam mattis id justo vitae rhoncus. Donec semper viverra ante ac commodo. Mauris et ex at erat egestas sollicitudin quis id libero. Quisque mi mi, facilisis nec tempor ac, feugiat at mi. Duis sollicitudin quis augue sit amet consectetur. Aenean ipsum diam, bibendum a turpis in, tempus ultricies lacus. Etiam varius risus eget diam faucibus eleifend. Donec laoreet justo et pretium porttitor.
Etiam in purus eget mauris consectetur fringilla. Nam ac odio sed erat ullamcorper luctus. Aliquam erat volutpat. Sed consequat dignissim metus elementum aliquam. Donec vitae justo vestibulum, fringilla eros vel, venenatis lectus. Vestibulum orci felis, sodales molestie porta eget, efficitur id sapien. Praesent ultrices, felis eget suscipit sollicitudin, ipsum diam mollis metus, et fermentum mi risus sed enim. Praesent commodo, sapien nec ullamcorper hendrerit, tortor erat consectetur sem, ultricies tincidunt diam risus nec metus.
Temporary compound at New Bridge Lane
Installation of automated gates in the fence, and restoration of the land at 10 Newbridge lane.
Water vole mitigation
Construction package 1
Installation of an acoustic fence along the boundary of a residential property on New Bridge Lane.
Initial Work
Deliver materials to the temporary compound, prepare holes for fence posts, and installation of fence posts and gate pads.
Fencing Works
Completing fencing foundations, taking delivery of fence gates and installing concrete fence panels and gates.
Gate Works
Finalise installation of fence panels and gates, including paint on both sides.
Snagging
Delivery of secondary gates, including installation of front and side access gates. Also includes snagging and demobilisation.
Construction Package 3
Main Energy from Waste Combined Heat and Power Facility construction site. Creation of a temporary construction compound at the end of Algores Way.
Initial Works
Deliver and install temporary welfare cabins, while the previous tenant or landowner removes the existing shed (kept fenced off until complete). Once cleared, relocate the welfare cabins to the vacant shed area, then carry out earthworks to form temporary ramps, haul roads, and hardstandings, followed by piling using non-percussive rigs.
Piling
Carry out piling using non-percussive rigs, grout the secant piles forming the waste bunker walls, and excavate for the waste bunker.
Base Wall Construction
Set up the slip form rig for concrete pours, then construct the waste bunker slab and base wall.
Main Walls
Start pouring concrete for main building walls and start ground improvements around waste bunker.
Main Building
Pour concrete slabs for main building and erect steelwork for waste bunker.